A.Hak Drillcon recently completed one of the most complex and challenging projects in its history. For this project, dubbed the ‘Elbedüker’, the drilling expert was selected as the main contractor by customers Gasunie Deutschland Transport Services, Open Grid Europe, Deutsche Telekom and WSA-Hamburg.

In this project, a tunnel with a 1,528 meter length was constructed under the Elbe River in Hetlingen, close to Hamburg. At that time it was the largest European tunnel project in progress. At a depth of 40 meters under the river, a concrete jacket pipe with a three meter diameter is installed. This pipeline will accommodate two high pressure gas pipelines that guarantee the gas supply for Northern Germany and Scandinavia.

As the main contractor, A.Hak Drillcon solved numerous technical challenges while fully complying with the stringent Quality, Health, Safety and Environment requirements.

  • news

    River crossings TAP River crossings TAP

    River crossings TAP

    A.Hak is proud of its own equipment that is used in the construction of underground infrastructure all over the world. Our machines demand a leading role on film material from the TAP project.

  • news

    A.Hak wins Tytan Award 2017 A.Hak wins Tytan Award 2017

    A.Hak wins Tytan Award 2017

    A.Hak Leidingbouw won the Tytan Award 2017 with the rehabilitation of a production water pipeline by means of a trenchless pipe-in-pipe method for client Nederlandse Aardolie Maatschappij BV (NAM).

  • news

    Winner ISTT No-Dig Award 2016 Winner ISTT No-Dig Award 2016

    Winner ISTT No-Dig Award 2016

    A.Hak Leidingbouw wins ISTT No Dig Annual Award 2016 in the category for Project Rehabilitation with the Unique pipe-in-pipe project for NAM.

  • projects

    Oil pipeline Fier Albania Oil pipeline Fier Albania

    Oil pipeline Fier Albania

    A.Hak International partnered up with A.Hak Drillcon to built an oil pipeline between the Albanian places Fier and Vlore. This job required 18 HDD drillings.